Our Project - TM Partner
Metro - E (NPE & EPE)
- Conducted engineering site survey.
- Install Metro
- E equipment at site once the survey report has been approved.
- Performed testing & commissioning after the installation completed by using using PON power meter.
- Prepare acceptance testing report for customer before hand over.
- Install Metro
- E equipment at site once the survey report has been approved.
- Performed testing & commissioning after the installation completed by using using PON power meter.
- Prepare acceptance testing report for customer before hand over.
OLT (optical line terminal)
- Conducted engineering site survey before equipment deployment.
- Install equipment MA 5600T at site once the survey report has been approved.
- Performed testing & commissioning after installation by using test gear PON power meter and variable attenuator.
- prepare acceptance test report for customer before hand over.
- Install equipment MA 5600T at site once the survey report has been approved.
- Performed testing & commissioning after installation by using test gear PON power meter and variable attenuator.
- prepare acceptance test report for customer before hand over.
VDSL
- Performed testing & commissioning by using VDSL modem to make sure there are three services available such as voice, internet. and IPTV.
- Prepared acceptance test report for customer before hand over take place.
- Prepared acceptance test report for customer before hand over take place.
Wifi outdoor installation
- Installed the 2.4Ghz antenna for point to point communication.
- We were doing alignment to make the antenna able to communicate with each other.
- Besides, we also installed access controller, switch and modem to complete the installation
- We were doing alignment to make the antenna able to communicate with each other.
- Besides, we also installed access controller, switch and modem to complete the installation
NGN (HUAWEI)
- Conducted engineering site survey
- Install the equipment after all technical site survey has been approved
- Perform testing and commissioning after the installation complete
- Prepare the acceptance test document and hand over to customer
- Install the equipment after all technical site survey has been approved
- Perform testing and commissioning after the installation complete
- Prepare the acceptance test document and hand over to customer
Project - Maxis
CX 600
- Conducted engineering site survey.
- Deployed equipment Cx 600 router after the survey report approved.
- Cx 600 router is connected to OLT (optical line terminal)
- Deployed equipment Cx 600 router after the survey report approved.
- Cx 600 router is connected to OLT (optical line terminal)
OLT (optical line terminal)
- Conducted engineering site survey.
- install equipment MA 56O0T at site after survey report approved.
- Performed testing & commissioning by using PON power meter and variable attenuator to make sure there are three services available such as voice, internet. and IPTV.
- prepare user acceptance test report for client before hand over.
- install equipment MA 56O0T at site after survey report approved.
- Performed testing & commissioning by using PON power meter and variable attenuator to make sure there are three services available such as voice, internet. and IPTV.
- prepare user acceptance test report for client before hand over.
MXU (MA 5612)
- Conducted engineering site survey.
- After survey report approved then proceed with equipment installation at site
- Performed testing & commissioning by using test gear Ethersam to test for packet trans mission and to make sure there is no packet loss.
- Prepare acceptance test report to client before handover.
- Migrate the existing node B to MxU (MA 5612) in order to upgrade it to the higher bandwidth.
- After survey report approved then proceed with equipment installation at site
- Performed testing & commissioning by using test gear Ethersam to test for packet trans mission and to make sure there is no packet loss.
- Prepare acceptance test report to client before handover.
- Migrate the existing node B to MxU (MA 5612) in order to upgrade it to the higher bandwidth.
Home pass & maintenance work
- Lay 1 pair of fiber optic cable from distribution point to customer house.
- Once the ï¬Âber optic cable is lay. performed splicing for both end ï¬Âber optic cable to bridge the connection.
- Performed test to verify the services are up such as voice, internet and IPTV.
- For maintenance, our team performed troubleshooting in order to identify thecause of the services break down.
- Once the ï¬Âber optic cable is lay. performed splicing for both end ï¬Âber optic cable to bridge the connection.
- Performed test to verify the services are up such as voice, internet and IPTV.
- For maintenance, our team performed troubleshooting in order to identify thecause of the services break down.
DBKL PROJECT - VMS (Vehicle Management System)
We installed the cabling system for this project such as G.I. conduit, power cable, VMS DB, catweld earthing and others.
- We have installed the VMS DB in order for DBKL to control the digital signage display remotely.
- We have installed the VMS DB in order for DBKL to control the digital signage display remotely.